If you are sure that you want to be better, then you must start taking some measures. Selecting CCM practice prep may be your key step. If you are determined to pass the exam, our study materials can provide you with everything you need. You can have the learning materials, study plans and necessary supervision you need. You will have no reason to stop halfway. With CCM learning materials, you can definitely stick to your goals. You can imagine how fascinating you will be! So, take a look at the advantages of our study materials! Trust me, you will love our CCM study guide.
Perfect service system
If you are very tangled in choosing a version of CCM practice prep, or if you have any difficulty in using it, you can get our help. We provide you with two kinds of consulting channels. You can contact our online staff or you can choose to email us. No matter which method you choose, CCM learning materials guarantee that we will reply to you as quickly as possible. We hope you can feel that we sincerely hope to help you. We hope that after choosing our study materials, you will be able to concentrate on learning our CCM study guide without worry. It is our greatest honor that you can feel satisfied. Of course, we will value every user. We will never neglect any user. Our study materials will provide perfect service for everyone.
Free trial version
In the current market, there are too many products of the same type. It is actually very difficult to select the CCM practice prep that you love the most with only product introduction. Our trial version of our study materials can be a good solution to this problem. If you are not sure whether our product is suitable for you, you can request to use our trial version. Of course, CCM learning materials produced several versions of the product to meet the requirements of different users. You can also ask to try more than one version and choose the one that suits you best. Prior to this, please inform us of your email address on the CCM study guide so that we can send you a free demo of our study materials. We hope that the study materials you purchased are the best for you.
Learn anytime, anywhere
CCM practice prep broke the limitations of devices and networks. You can learn anytime, anywhere. As long as you are convenient, you can choose to use a computer to learn, you can also choose to use mobile phone learning. No matter where you are, you can choose your favorite equipment to study our CCM learning materials. With regard to the Internet, if you use our study materials in a network environment, then you can use our products in a non-network environment. CCM study guide guarantee that you can make full use of all your free time to learn, if you like. The reason why we emphasize this is that we know you have a lot of other things to do. Many users stated that they can only use fragmented time to learn. Experts at CCM practice prep also fully considered this point.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?
Choose all of the correct answers (multiple possibilities).
A) Specification
B) General Conditions of Contract
C) Employer ' s Requirements
D) Special Conditions
2. (Please select the one answer in which the mentioned documents are in the correct order (hierarchy), as mentioned in the standard Contract Agreement form of the FIDIC Silver Book (edition 1999).)
A) Contract Agreement, Addenda, Conditions of Contract, Employer's Requirements, Contractor ' s Tender.
B) Contract Agreement, Conditions of Contract, Addenda, Contractor ' s Tender, Employer's Requirements.
C) Contract Agreement, Conditions of Contract, Employer's Requirements, Contractor ' s Tender, Addenda.
D) Contract Agreement, Conditions of Contract, Addenda, Employer's Requirements, Contractor ' s Tender.
3. You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?
A) None of the above.
B) Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.
C) Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.
D) Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.
4. A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months.
This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?
A) The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.
B) If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.
C) If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.
D) In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.
5. (Under the FIDIC Red and Yellow Books (edition 1999), which two of the following answers are correct regarding the application for Interim Payment Certificates? Choose all correct answers.)
A) Each statement must be accompanied (or preceded) by supporting documents, including the progress report specified in Sub-Clause 4.21, for the relevant period.
B) The statement submitted by the Contractor shall include, if applicable, any amounts to be added and deducted for Plant and Materials.
C) The statement submitted by the Contractor shall include, if applicable, any amounts to be added for Provisional Sums.
D) The Contractor shall submit a Statement in five copies to the Employer.
Solutions:
| Question # 1 Answer: C,D | Question # 2 Answer: D | Question # 3 Answer: C | Question # 4 Answer: D | Question # 5 Answer: A,C |