NEW QUESTION 89
What would prevent a program manager from completing program closure once a program has been completed?
- A. Failure to obtain program steering committee approval
- B. Incomplete realization of all program benefits
- C. Failure to update the financial management plan
- D. Failure to update the benefits register
Answer: A
NEW QUESTION 90
A program has been established and preparation is complete. Component projects are planned as a part of which of the following?
- A. Program formulation
- B. Program planning
- C. Program delivery phase
- D. Program definition phase
Answer: C
NEW QUESTION 91
In order for an ICT distribution designer to identify the BEST solutions for the client's needs they may have to provide
- A. subcontractors lists
- B. shop drawings
- C. Operation and Maintenance manuals
- D. material lists (e.g., BOM).
Answer: D
NEW QUESTION 92
Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B's program manager has just advised that program B has been closed.
What should program A's program manager update and review first with the stakeholders?
- A. Benefits management plan
- B. Benefits transition plan
- C. Benefits register
- D. Benefits sustainment plan
Answer: D
NEW QUESTION 93
You are designing distribution for a seven unit townhouse with in slab conduits. What is the MINIMUM number of 27 mm (1 in) rigid PVC Type 2 or metallic conduit that is required to satisfy distribution to each unit?
- A. Fourteen
- B. Seven
- C. Three
- D. Four
- E. Five
Answer: B
NEW QUESTION 94
In new construction, what is the percentage of pay phones that must be equipped with volume controls?
- A. 0
- B. 1
- C. 2
- D. 3
- E. 4
Answer: D
NEW QUESTION 95
What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?
- A. As part of the contract bid process to prevent project delays
- B. At the beginning of the close out process
- C. Before the contract is awarded
- D. After the contract is awarded and before project close out
Answer: D
NEW QUESTION 96
A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline What key elements should be included in the benefits register to achieve this goal?
- A. Plans for tracking and communicating risks associated with the program
- B. Plans for program schedule control to meet the shorter timeline
- C. Plans for defining metrics and key performance indicators (KPIs), and procedures to measure benefits
- D. Plans for conducting program quality assurance and control on a regular basis
Answer: C
NEW QUESTION 97
Communicating a project's design and technical specifications to the client and stakeholders is part of the
___________of the project.
- A. needs analysis
- B. close out procedure
- C. scope of work
- D. bidding phase
Answer: C
NEW QUESTION 98
A company wants to perform a preliminary stakeholder analysis lo assess a new program's support. What should the program manager develop'?
- A. Stakeholder engagement plan, stakeholder register, and stakeholder map
- B. Responsible accountable consult and inform (RACI) matrix stakeholder list, and escalation process
- C. Stakeholder strengths weaknesses, opportunities and threats (SWOT) analysis
- D. Program communications management plan and the stakeholder charter
Answer: A
NEW QUESTION 99
During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?
- A. Execute the component project's communications management plan
- B. Review and update the detailed stakeholder list
- C. Update the risk register.
- D. Review and update the stakeholder engagement plan
Answer: D
NEW QUESTION 100
Which two of the following are means in which radiated interference primarily enters electronic devices?
(Select two options.)
- A. Interface designs
- B. Missing or inadequate device or cable shielding
- C. Proximity to interfering sources
- D. Input signal lines
- E. Missing or inadequate optical connections
Answer: B,C
NEW QUESTION 101
A critical program for a company fails lo delivers its intended benefits. The CEO and program sponsor are both held accountable and. ultimately, their employment is terminated by the board of directors What should the program manager do before formally closing the program?
- A. Update the benefits register
- B. Transfer all program documentation to the deputy program manager
- C. Share lessons learned with an program team members
- D. Establish a program management information system (PMIS)
Answer: C
NEW QUESTION 102
What is the MINIMUM distance from the edge of a pool or other water hazards for a weatherproof enclosure?
- A. 4 m (13 ft)
- B. 10 m (30 ft)
- C. 2 m (7 ft)
- D. 1 m (3 ft)
- E. 6 m (20 ft)
Answer: E
NEW QUESTION 103
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff What should the program manager do to ensure communications on the component projects are consistent?
- A. Request a more experienced project manager to work on project 6
- B. Direct all projects to use project A's communications management plan as a template
- C. Rework the communications management plans for all projects to be consistent
- D. Create a program communications management plan across all component projects
Answer: C
NEW QUESTION 104
An ICT distribution designer is designing a backbone cabling network that is specified for a campus network including several links approaching 2000 m (6562 It) and data rates of 100 Gb/s What optical fiber type(s) should be used?
- A. OM3 fiber
- B. OM4 fiber
- C. Both OS2 and OM3 fiber
- D. Both OS1 and OS2 fiber
Answer: D
NEW QUESTION 105
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
- A. Program sponsor
- B. Communications manager
- C. Project manager
- D. Program manager
Answer: D
NEW QUESTION 106
A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits (hat the program should deliver and has requested that the program manager determine when incremental benefits can be realized.
What should the program manager do first?
- A. Develop the program roadmap
- B. Develop the benefits sustainment plan
- C. Develop the component project schedules
- D. Develop the program management plan
Answer: A
NEW QUESTION 107
Identify the fibers below as either single mode (SM) or multi-mode (MM) by dragging the appropriate term into each oval.
Answer:
Explanation:

NEW QUESTION 108
AI the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company's strategy During the previous year, the company needed to comply with new government regulations that impacted this strategy.
Based on this information, what should the program manager do?
- A. Review resource capacity and capability, program priorities, and inter dependencies, and create a change request to modify the program roadmap to ensure strategic alignment
- B. Meet with stakeholders, and modify the program roadmap to comply with the new regulations and ensure strategic alignment
- C. Update the program management, benefits management and risk management plans, and modify priorities and inter dependencies
- D. Obtain stakeholder approval to stop or postpone programs that fail to comply with the new regulations, and modify the program roadmap
Answer: C
NEW QUESTION 109
A program manager needs to establish direction and identity the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined assessed and documented Which document will be created to support this activity?
- A. Program scope statement
- B. Program resource management plan
- C. Program management plan
- D. Program master schedule
Answer: A
NEW QUESTION 110
A system integration approach of a BAS on to a LAN can usually reduce the cost of cabling-related changes by
- A. 50 percent
- B. 25 to 40 percent
- C. 10 to 20 percent
- D. 45 percent
Answer: B
NEW QUESTION 111
......
Get Ready with RCDDv14 Exam Dumps (2022): https://actualtests.real4prep.com/RCDDv14-exam.html